Forecast what your project will actually cost. Enter your budget, earned value and actual cost, and get your Estimate at Completion, the estimate to complete, and how far over or under budget you're heading.
The Estimate at Completion (EAC) is the forecast total cost of a project given how it's performing so far. Where BAC is what you planned to spend, EAC is what you now expect to spend. The gap between them — the variance at completion (VAC) — is the early warning every budget owner wants.
This is the most widely used EAC formula. It assumes your current cost efficiency (CPI) continues for the rest of the work. From it: ETC = EAC − AC (the cost of the work still to come) and VAC = BAC − EAC (how far over or under you'll land).
A $4.2M project (BAC) has earned $1.85M of work (EV) and spent $1.9M (AC). CPI = 1.85 / 1.9 = 0.97. So EAC = 4.2 / 0.97 = $4.33M, ETC = 4.33 − 1.9 = $2.43M still to spend, and VAC = 4.2 − 4.33 = −$130k — a forecast $130k overrun. A 3% cost slip today becomes a six-figure miss at completion, which is exactly why EAC is worth watching from early on.
When the overrun to date is a one-off, use EAC = AC + (BAC − EV) — the remaining work reverts to plan. When both cost and schedule pressure will persist, use EAC = AC + (BAC − EV) / (CPI × SPI). This tool uses the standard BAC / CPI; the full earned value calculator shows the inputs behind all three.
EAC (Estimate at Completion) is the forecast total cost based on performance to date. The common formula is EAC = BAC / CPI.
EAC = BAC / CPI, where CPI = EV / AC. A $4.2M budget at CPI 0.97 forecasts EAC ≈ $4.33M.
BAC / CPI (efficiency continues); AC + (BAC − EV) (remaining reverts to plan); AC + (BAC − EV) / (CPI × SPI) (cost and schedule persist). This tool uses BAC / CPI.
Aegis computes EAC from your live schedule every period and pairs it with a 1,500-run Monte-Carlo completion date — so your cost and time forecasts come from the same source of truth.
Start free with your own project →